I Percented Everything to 100% in DPC Complete but Project does not show 100% Complete Overall

Reference Number: AA-00658 Views: 2430 Created: 01/27/2016 10:37 am Last Updated: 02/22/2018 01:24 pm 0 Rating/ Voters

So, you have set all your takeoff objects for all Cost Codes to 100%, but your Total % Complete is not 100%.

Why is my Project not 100% Complete?

The answer is "Indirect Expenses". Indirect Expenses are applied to Cost Codes automatically, but only get 'percented' as Time is entered on the Timecard Tab (labor is used). If you do not track labor expenses on the Timecard Tab, your project may never show Total 100% complete.

This only applies to Indirect Expenses that use Labor Hours as Calculation method and Labor Cost as the result or use Duration for Supervision. (Material costs are ignored by Digital Production Control.)


Discussion
  • There is no feedback for this article.
Info Anything Wrong with this Article?

Please tell us your suggestion for making this article better:

Your full name: Your Email: Your feedback on this article:

 
Be sure to subscribe to comments so you are notified when there is a response to your comment.

If you need Technical Support or want to submit a Feature Request, click one of the buttons below, do not use this form.

 
request support Request Support submit feature request Feature Request

 


 

Something Wrong with this Article? Let us Know! Copyright 2018 - On Center Software, Inc. All Rights Reserved.
Be sure to rate this article 5 stars if you found it helpful!.